Designing and managing the implementation and operation of Egyptian Governmental Fiscal Management Information System

15000 people affected
7 people managed
12 month project

Project Description

1- Creating 3 plans to start the services in the shortest time. These are short term, mid term and long term plans.

2- Communicating with different vendors to achieve the best scalable and cost effective solution.

3- Ordering hardware and software needed for the project.

4- Building IT team to follow up implementation and operation of the whole project hardware and software.

5- Managing the operation team of the project to achieve 24X7 services availability.

Highlights

Under budget

Difficulties

Large no. of people impacted

Products Used

Technical Skills Used

  • Analysis and evaluation of HW and SW
  • Complete solution design
  • Cairo (EG)30.062631.2497